Experiences

AV Group Nackawick
Project Description:
Engineering, procurement, fabrication and installation of Recovery Boiler Economizer.
Reference:
John Bartlett
Project Manager
C: 506-476-5600
John.Bartlett@avg.adityabirla.com
Timeline:
June 2021 – October 2021
Project Information:
- Over 42,000 feet of tubes to prepare and bend
- Machining of twelve headers (over 1,700 tube seats)
- Assembly of six modules (over 1,700 welded joints)

Cavendish Farms
Project Description:
Cavendish Farms plant required fabrication and installation of two CO2 refrigeration units.
Reference:
Craig Perry P. Eng
Engineering Project Manager
C: 506-380-3300
Perry.Craig@jdirving.com
Timeline:
Phase-I : Dec 2020 – Mar 2021
Phase-II : Nov 2021 – Mar 2022
Project Information:
MPW was a general contractor for the fabrication management and install of:
- Two CO2 refrigeration skids
- Six evaporator units, CO2 tubing and glycol piping runs
- Glycol equipment (pumps, tanks, valves etc.)

HMCS Harry DeWolf
Project Description:
HMCS Harry DeWolfe post delivery, Ongoing maintenance contract with Thales Group Canada
Reference:
Todd Kennedy
902-401-7846
Todd.Kennedy@thalesgroup.com
Timeline:
Nov 30th 2020 – Ongoing
Project Information:
Provide mechanical and hull sub-contract support for on-going maintenance aboard HMCS Harry DeWolfe, as well as the rest of the fleet

HMCS Fredericton
Project Description:
HMCS Fredericton underwent a refit at Irving Shipbuilding. Also shortly afterwards, an Engineering
Change (EC) was performed at CFB Halifax
Reference:
James Mason
Contract Manager – Irving Shipbuilding
902-430-3120
Mason.james@irvingshipbuilding.com
Timeline:
Refit: March 2017 – Jan 2019
Engineering Change: June 2020 – October 2020
Project Information:
Provide mechanical and hull sub-contract support throughout duration of the project. For EC, Maritime Pressure Works Ltd. provided support for Primary HVAC Control alterations

HMCS Charlottetown
Project Description:
HMCS Charlottetown underwent a refit at Irving Shipbuilding. A “PRE” and “post” dock work period was supported
Reference:
James Mason
Contract Manager – Irving Shipbuilding
902-430-3120
Mason.james@irvingshipbuilding.com
Timeline:
Pre Dock: May – June 2019
Refit: June 2019 – Feb 2021
Post Dock: Feb 2021 – June 2021
Project Information:
Provide mechanical and hull sub-contract support throughout duration of the project.